When in the schedule
The floor scrub belongs after the last trade that makes dust and before anything that makes the floor hard to reach. In practice that means:
- Drywall finish, paint, and ceiling work are complete.
- Overhead trades are out and their lifts are off the slab.
- The slab has been dry-swept and the piles removed.
- Racking, striping, fixtures, and FF&E have not gone in yet.
If racking install happens after the scrub, expect a second round of grit from the anchors and the forklifts. A lighter re-scrub after racking is common, and it is quoted below the first visit.
What a scrubber removes, and what it does not
An auto scrubber lifts:
- Drywall and joint-compound dust, including what has been walked into the pores
- Slab grit, sand, and the fine laitance a new floor sheds
- Light mortar and grout haze from tile and masonry work
- Joint-compound drips and small adhesive spots, with the right chemistry
- General residue: footprints, coffee, sawdust film, the gray of a months-old jobsite
A scrubber does not lift:
- Cured flooring adhesive fields
- Heavy mortar or thinset buildup
- Paint fields or heavy overspray
- Curing-compound residue on some slabs
- Anything that needs a surface profile for a coating
Those are mechanical-removal jobs, usually a grinder, and a floor contractor should say so during the walkthrough.
What a complete clean includes
- A walkthrough with the superintendent to confirm what is left on the slab, which trades are still coming, and what the punch list means by “clean”
- Anything that needs a grinder, named in the quote so nobody expects the scrubber to handle it
- Pickup of the screws, wire, banding, and debris the final sweep left behind
- A full-slab machine scrub, including the offices, restrooms, and corners, with the dirty water recovered
- Treatment of mortar haze, joint-compound drips, and adhesive spots
- A dry floor with no film, ready for the next crew, the striping, or the owner’s walkthrough
Common mistakes
- Scrubbing too early. Paint and drywall work after the scrub put dust back on the slab, and the floor has to be scrubbed again.
- Hosing the slab. Water without recovery pushes the dust into the joints and leaves a floor that dries hazy.
- Acid on a new slab. Muriatic acid has no place in a post-construction clean.
- Assuming the scrub preps for coatings. A coating needs the profile a grinder or shot-blaster leaves. A scrub before the coatings crew arrives removes the dust that would otherwise be ground into the slab; it does not replace the prep.
- Skipping the dry pickup. Screws, wire, and dust piles left on the slab add time and cost to the scrub.
What to send a floor contractor for a quote
Square footage, the floor type (bare, sealed, densified, or coated), what trades have been on it, your turnover date, and a few photos of the worst areas. For most shells that is enough to quote from plans; occupied buildings and heavy-residue floors get a walkthrough so the number is right.
How Maddox handles it
For general contractors, construction managers, and incoming tenants in Houston, Maddox schedules post-construction floor cleaning to the turnover date. A turnover date that moves by a day or two is absorbed without re-quoting.